Workshop needs tooling appropriate for production

Change Delete
Welder
UNASSIGNED
Change Delete
Verify Functionality of infrastructure
UNASSIGNED
Change Delete
Get Drill Press
UNASSIGNED
Change Delete
Workshop Chairs Stools
UNASSIGNED
Change Delete
Fix 2nd mill, not working on low speed
Graham and Yoonseo
Change Delete
Deploy plasma cutter
Graham and Yoonseo
Change Delete
Fix angle grinders
Marshall
Change Delete
Source mag drill
Marshall
Change Delete
Assess mag/ mill drill bits, 7/8" 5/8" 1/2"
Marshall
Change Delete
Enclose bays by building more shelves
Graham
Change Delete
Deploy power cube with Ironworker
Graham
Change Delete
Get the 3 phase welders running
Graham
Change Delete
3 phase converter and Pto Alternator
Graham
Change Delete
Welder wire spools
Graham
Change Delete
Power Cable on Bandsaw
Yoonseo
Change Delete
Source Cutting Fluid
Yoonseo
Change Delete
get generator welder up
Graham
Change Delete
Set up functional computer surface in workshop
Graham
Change Delete
Building Table in workshop
aidan
Change Delete
Source schrader tire valve
Graham
Change Delete
Digital Readouts for Mills
Yoonseo
Change Delete
Milling Vise
UNASSIGNED
Change Delete
Band Saw
Marshall
Change Delete
Fix 2nd millermatic
Graham
Change Delete
Source TIG aluminum welding wire from Sweiger
Graham
Change Delete
PTO Alternator Shaft Collar from Sweiger
Graham
Change Delete
Design of CEB press ready for full production

Change Delete
On Site CAE analysis
UNASSIGNED
Change Delete
Fastener design evaluation
Marshall
Change Delete
Hopper/Shaker 3D CAD 1
Marshall
Change Delete
Cylinder Design
Marshall
Change Delete
New Cylinder CAD
Marshall
Change Delete
Main Frame Assembly 3D CAD 1
Marshall
Change Delete
Hold and record Flash Mob for CEB Press
Marshall
Change Delete
CAD Fix bolts on main frame
UNASSIGNED
Change Delete
Github
Chris
Change Delete
Ask Microtrac CADer for help
Graham
Change Delete
Check torsion of cylinder
Marshall
Change Delete
Main Frame 3x6 U-Channel CAD
Marshall
Change Delete
rail follower holder CAD
Marshall
Change Delete
CAE options investigation
Alex Briggs
Change Delete
Pictures and Measurements from Zach
Marshall
Change Delete
Prepare Flash Mob matrial: problem statement
Marshall
Change Delete
Invite SME's to flash mob
Aaron
Change Delete
CEB Production Work flow including fab and documentation needs to be defined

Change Delete
Systems Engineering Breakdown Diagram
UNASSIGNED
Change Delete
CEB Module Interface Design
UNASSIGNED
Change Delete
Exploded Parts Diagram
UNASSIGNED
Change Delete
Documentation Plan for production run
Marshall
Change Delete
Delete/archive obsolete material on wiki
UNASSIGNED
Change Delete
Piece by piece fab instructions
Marshall
Change Delete
Bill of Materials
Marshall
Change Delete
Teach marshall the build diagram
Yoonseo
Change Delete
Build diagram
Marshall
Change Delete
Document Solenoid driver design
Yoonseo
Change Delete
Identify what pieces don't need to be purchased
Marshall
Change Delete
New design of CEB needs to be tested, and tests should modify design

Change Delete
Assemble CEB Controller case 
UNASSIGNED
Change Delete
Build CEB
UNASSIGNED
Change Delete
Document BUild
UNASSIGNED
Change Delete
Test CEB
UNASSIGNED
Change Delete
Document testing
UNASSIGNED
Change Delete
Change design per testing
UNASSIGNED
Change Delete
Source Materials
Marshall
Change Delete
Run Soil Tests in minimum 2 sites for extracting soil
Graham
Change Delete
Fabricate 1 
solenoid drivers
Yoonseo
Change Delete
Source solenoid driver
Yoonseo
Change Delete
Research Soil Mixture requirements
Graham
Change Delete
Determine if additives are necessary for creating good bricks
Graham
Change Delete
CEB Production = 8 people + 1 day

Change Delete
Source Materials
UNASSIGNED
Change Delete
Research material sourcing
UNASSIGNED
Change Delete
REsearch distribution options
UNASSIGNED
Change Delete
Research Market for sales
UNASSIGNED
Change Delete
Assign fab tasks
UNASSIGNED
Change Delete
Interactive ppt  idea map of fab steps
Marshall
Change Delete
Fab CEB
UNASSIGNED
Change Delete
Test CEB
UNASSIGNED
Change Delete
Pack and ship CEB
UNASSIGNED
Change Delete
Move metal from old shop
Graham
Change Delete
Replicable Enterprise

Change Delete
Create Business Plan
UNASSIGNED
Change Delete
Document samples
Graham
Change Delete
Experiment with CEB mixtures
Graham
Change Delete
Existing CEB Press functinal

Change Delete
Run CEB
UNASSIGNED
Change Delete
Truing CEB press
UNASSIGNED
Change Delete
Document CEB Test outcomes
UNASSIGNED
Change Delete
Build interface between board and case
Yoonseo
Change Delete
Install new CEB controller box
Yoonseo
Change Delete
Assemble Controller Box
Yoonseo
Change Delete
Revise and build2 terminal blck
Yoonseo
Change Delete
Build soleoid driver
Yoonseo
Change Delete
Build controller box
Yoonseo
Change Delete
Other Teams access to crucial milestones

Change Delete
Scrum with Calendar
Graham
Change Delete
New Story

                

Feedback:








Loading...

Scrumy The Scrumy name, logo, and design are copyright © 2013
Feedback Local Settings
Swimlanes Grid High contrast
About API Contact Blog